In proceeding 27062, ATCO Electric Transmission (ATCO) submit its 2023-2025 general tariff application to the Alberta Utilities Commission (the Commission) for approval. In August 2022, the Commission approved ATCO and the Interveners to enter a negotiated settlement process, and the parties engaged in settlement negotiations starting December 12. By December 20, all parties agreed in principle to a negotiated settlement. ATCO now requests that the Commission approve the settlement agreement and the resulting adjustments.[1]