ATCO PBR2 Plan Review – Evidence and Arguments

In proceeding 28300, the Alberta Utilities Commission (the Commission) hears arguments for and against whether the plan for the second term of performance-based regulation (PBR2) of ATCO Gas and ATCO Electric (ATCO) was flawed; and if so, whether it is reasonable to re-open the plan. In proceeding 20414, the Commission set out a reopener provision allowing for the review of PBR plans if a utility’s return on equity (ROE) is 300 basis points above or below the approved ROE for two consecutive years, or if it is above or below 500 points in a single year. ATCO exceeded the 300-basis point threshold for 2021 and the 500-basis point threshold for 2022, triggering this current proceeding.[1]



To view more of this post, please

Login Here

or contact us.