AltaLink Application Regarding Destroyed Assets

In proceeding 28750, AltaLink Management Ltd. (AltaLink) applies to recover its expenditures incurred to repair, replace, and salvage its transmission facilities that were damaged or destroyed in the 2023 Spring wildfire and snow events. AltaLink calculates that the total expenditure is $24.7 million, which it requests to be included in its 2024 opening rate base and net salvage reserve where applicable. AltaLink is filing this application now because it only recently finished determining the total scope of repair and expenditures and the 2023 Spring wildfire and snow events occurred after AltaLink filed its 2024-2025 GTA which is currently being considered in proceeding 28174.[1]



To view more of this post, please

Login Here

or contact us.

Decision on ENMAX’s 2023-2025 Transmission General Tariff Application

In proceeding 27581, the Alberta Utilities Commission (the Commission) issues its decision regarding the 2023-2025 Transmission General Tariff Application of ENMAX Energy Corporation (ENAMX) in which ENMAX entered a negotiated settlement with interveners. The Commission notes that this decision was originally supposed to have been released in July of 2023, but was delayed after it was learned that ENMAX was being investigated by Commission Enforcement staff regarding the year-end capitalization of certain distribution and transmission projects. The investigation is ongoing, but the Commission understands that the investigation results are unlikely to have a material impact on this decision.[1]



To view more of this post, please

Login Here

or contact us.

TransAlta’s 2022-2023 GTA Decision

In proceeding 27964, the Alberta Utilities Commission (the Commission) issues its decision on the 2022-2023 general tariff application of TransAlta Corporation (TransAlta). TransAlta requested a $9.0 million revenue requirement for 2022 and $9.4 million for 2023. The three main contentions in this proceeding centered around TransAlta’s non-union salary escalation rates, its operations and maintenance (O&M) agreement with AltaLink Management Ltd. (AltaLink), and its First Nations Advisory Committee costs.[1]



To view more of this post, please

Login Here

or contact us.

AltaLink’s 2024-2025 General Tariff Application

In Proceeding 28174, AltaLink Management Ltd. (AltaLink) submits to the Alberta Utilities Commission (the Commission) its 2024-2025 general tariff application along with the applications of KainaiLink, L.P. (KainaiLink) and PiikaniLink, L.P. (PiikaniLink) for review. Overall, AltaLink seeks to maintain its transmission tariffs at its 2018 levels and to correct accounting errors discovered since its previous application.[1]



To view more of this post, please

Login Here

or contact us.

ATCO Electric’s 2023-2025 General Tariff Application Decision

In Proceeding 27062, the Alberta Utilities Commission (the Commission) decides on the 2023-2025 General Tariff Application of ATCO Electric Ltd. (ATCO). The Commission allowed ATCO and interveners to enter a negotiated settlement process on all matters except for the Vegetation Management reserve removal and modifications to ATCO’s Variable Pay Program reserve. Parties were also unable to agree on the treatment of the $7.5 million undepreciated balance for ATCO’s Jasper Palisades isolated generation plant. Therefore, the Commission dealt with these three issues separately from the negotiated settlement.[1]



To view more of this post, please

Login Here

or contact us.

EPCOR’s 2023-2025 General Tariff Application Decision

In proceeding 27675, the Alberta Utilities Commission (the Commission) issues its decision regarding the 2023-2025 general tariff application (GTA) of EPCOR Transmission & Distribution Inc. (EPCOR). Rather than proceed through an argument process, EPCOR negotiated a settlement with the Consumer’s Coalition of Alberta (CCA) and the Utilities Consumer Advocate (UCA). After review, the Commission approves EPCOR’s 2023-2025 GTA, which includes the negotiated settlement reduction of $10.81 million, the withdrawal of EPCOR’s request for a cloud-based software as a service (SaaS) cost deferral account, and compliance with Commission decisions.



To view more of this post, please

Login Here

or contact us.

ATCO Electric Transmission 2023-2025 Tariff Application Arguments

In Proceeding 27062, ATCO Electric Transmission (ATCO) submit its 2023-2025 general tariff application to the Alberta Utilities Commission (the Commission) for approval. In December 2022, all parties agreed to a negotiated settlement, which the Commission approved in January 2023. However, the settlement excluded the three following matters:

  • A depreciation adjustment related to the Jasper Palisades Isolated Generation Plant.
  • Modification to the variable pay program.
  • Vegetation management reserve removal.

The intervening parties submit their oral arguments that address these three remaining issues.



To view more of this post, please

Login Here

or contact us.

TransAlta’s 2022-2023 General Tariff Transmission Application

In proceeding 27964, TransAlta Corporation requests approval of a $9.0 million revenue requirement for 2022 and $9.4 million for 2023, along with a one-time payment from the Alberta Electric System Operator (AESO) of $846,000 to reconcile approved interim rates. This revenue requirement includes TransAlta’s transmission facility owner rates applicable to the AESO’s use of TransAlta’s transmission facilities over the test period and TransAlta’s costs associated with the Operations and Maintenance Agreement between AltaLink Management Ltd. (AltaLink) and TransAlta.[1]



To view more of this post, please

Login Here

or contact us.

Information Requests and Responses in ENMAX’s 2023-2025 Transmission General Tariff Application

In proceeding 27581, the Alberta Utilities Commission (the Commission), the Consumers’ Coalition of Alberta (CCA), and the Utilities Consumer Advocate (UCA) each submit their information requests (IRs) to ENMAX Energy Corporation (ENMAX) regarding ENMAX’s 2023-2025 Transmission General Tariff Application. ENMAX recently responded to these IRs that covered operations and maintenance costs, depreciation practices, and specific projects and programs.



To view more of this post, please

Login Here

or contact us.

Evidence regarding ATCO Electric’s Transmission 2023-2025 General Tariff Application

In Proceeding 27062, ATCO Electric Ltd. (ATCO) asks the Commission to approve their revenue requirement of $677.1 million in 2023, $687.8 million in 2024 and $698.6 million in 2025. ATCO notes that the 2023 requirement is lower than their 2022 forecast because they are proposing to stop collecting Future Income Tax (FIT) expenses, their property taxes are lower, and there are fewer head office costs. After completing a round of information requests, intervenors submitted evidence detailing their concerns regarding the application.[1]



To view more of this post, please

Login Here

or contact us.