In proceeding 31102, the Consumers’ Coalition of Alberta (CCA) applied to the Alberta Utilities Commission (the Commission or AUC) for reconsideration of its decision to deny the CCA standing in Proceeding 30955.
To view more of this post, please
In proceeding 31102, the Consumers’ Coalition of Alberta (CCA) applied to the Alberta Utilities Commission (the Commission or AUC) for reconsideration of its decision to deny the CCA standing in Proceeding 30955.
In proceeding 30323, the Alberta Utilities Commission (AUC or Commission) issued its final decision with respect to ATCO Electric Transmission (ATCO)’s 2026-2027 general tariff application (GTA) and its 2022-2024 deferral application.
In proceeding 30323, ATCO Electric Transmission (ATCO) applied to the Alberta Utilities Commission (AUC) for approval of a negotiated settlement agreement (NSA) between itself, the Consumers’ Coalition of Alberta (CCA), the Office of the Utilities Consumer Advocate (UCA) and the Industrial Power Consumers Association of Alberta (IPCAA), in respect of ATCO’s 2026-2027 general tariff application (GTA).
In Proceeding 30031, the Alberta Utilities Commission (AUC or Commission) issued its final decision regarding EPCOR Distribution & Transmission Inc.’s (EDTI) 2026–2027 general tariff application (GTA). In its decision, the Commission provided the rationale for its earlier approval of the negotiated settlement agreement (NSA) and addressed the remaining issues that were not resolved through the settlement process.
In Proceeding 29879, the Alberta Utilities Commission (AUC or Commission) issued its decision on four applications filed by AltaLink Management Ltd. on behalf of it and its affiliated entities: AltaLink Limited Partnership, PiikaniLink L.P., and KainaiLink L.P. (collectively referred to as AltaLink).[1]
Because the parties had already negotiated and submitted a settlement agreement, the Commission’s decision addressed only the matters that were not resolved within that agreement.
In Proceeding 30323, ATCO Electric Transmission (AET or ATCO) filed its 2026–2027 General Tariff Application (GTA) and its 2022–2024 Deferral Application with the Alberta Utilities Commission (AUC or Commission). The Consumers’ Coalition of Alberta (CCA) and the Office of the Utilities Consumer Advocate (UCA) both registered as interveners within the proceeding.
In Proceeding 30031, EPCOR Distribution & Transmission Inc. (EDTI or EPCOR) applied to the Alberta Utilities Commission (AUC or the Commission) for approval of a Negotiated Settlement Agreement (NSA) with the Office of the Utilities Consumer Advocate (UCA) and the Consumers’ Coalition of Alberta (CCA). Parties also submitted final arguments and reply.
In proceeding 30154, the Alberta Utilities Commission (AUC or Commission) issued its decision on the review and variance application filed by TransAlta Corporation (TransAlta). The application sought to vary Decision 29615-D01-2025, which had addressed TransAlta’s 2024–2025 General Tariff Application (GTA) and, in particular, its requested expenditures for fire risk mitigation and transmission line rebuilds.
In proceeding 30154, TransAlta Generation Partnership (TransAlta) applies to the Alberta Utilities Commission (AUC or Commission) to vary Decision 29615-D01-2025 (the Decision).
In Proceeding 30031, EPCOR Distribution & Transmission Inc. (EDTI or EPCOR) has applied to the Alberta Utilities Commission (AUC or the Commission) for approval of its Transmission General Tariff Application (GTA) for the 2026–2027 test period. EPCOR is seeking approval of forecast revenue requirements of $142.24 million for 2026 and $150.27 million for 2027.