In Proceeding 27062, ATCO Electric Transmission (ATCO) submit its 2023-2025 general tariff application to the Alberta Utilities Commission (the Commission) for approval. In December 2022, all parties agreed to a negotiated settlement, which the Commission approved in January 2023. However, the settlement excluded the three following matters:
- A depreciation adjustment related to the Jasper Palisades Isolated Generation Plant.
- Modification to the variable pay program.
- Vegetation management reserve removal.
The intervening parties submit their oral arguments that address these three remaining issues.