On July 4, 2019, the AUC released a decision on Proceeding 22742 regarding ATCO Electric Ltd.’s 2018 – 2019 Transmission General Tariff Application.
To view more of this post, please
On July 4, 2019, the AUC released a decision on Proceeding 22742 regarding ATCO Electric Ltd.’s 2018 – 2019 Transmission General Tariff Application.
At the end of July 2019, EDTI submitted a Transmission Facility Owner General Tariff Application for 2020-2022, resulting in Proceeding 24798 at the Alberta Utilities Commission.
Participants from the Capacity Market Rules Proceeding are now applying for cost reimbursement as part of Proceeding 24762. The total costs claimed are more than $2.1 million.
The Alberta Utilities Commission (the Commission) initiated Proceeding 24405 to determine what rate treatment should be given to distribution utilities that acquire electric or gas distribution systems from Rural Electrification Associations (REAs), municipalities or gas co-ops under the Performance Based Regulation (PBR) 2013-2017 framework and the PBR 2018-2022 framework.[1]
In July 2019, Altalink L.P. applied to the Alberta Utilities Commission in Proceeding 23848 for approval of a negotiated settlement agreement for Altalink’s 2019-2021 General Tariff Application. The agreement involved Altalink and four consumer advocate groups.
In February 2019, the Alberta Utilities Commission released a decision in Proceeding 23418 regarding EPCOR Water’s application to construct and operate a solar power plant to be used to supply an adjacent water treatment plant.
AltaLink Management Ltd. (AltaLink) filed responses to the first round of information requests from interveners regarding its 2019-2021 General Tariff Application (GTA) in Proceeding 23848.
On April 26, 2019, the Alberta Electric System Operator (AESO) and interveners filed arguments regarding the AESO’s proposed changes to metering processes and distribution-connected generation (DCG) in its 2018 Tariff Application, (Proceeding 22942).
On April 26, 2019, the Alberta Electric System Operator (AESO) and interveners filed arguments regarding the AESO’s 2018 Tariff Application (Proceeding 22942).
On April 5, 2019, ATCO Electric Ltd. (ATCO) and the Consumer’s Coalition of Alberta (CCA) filed arguments regarding the treatment of the direct assign capital deferral account in ATCO’s 2018-2019 General Tariff Application (GTA), Proceeding # 22742.