On August 18, the Alberta Utilities Commission (AUC) reopened ATCO Electric Ltd.’s 2018-2020 (now 2018-2021) deferral account application (Proceeding 26573).
On October 7, 2021, the AUC temporarily suspended ATCO Electric’s deferral account disposition in response to a complaint that costs related to the Jasper Interconnection Project were not prudently incurred. Specifically, through an investigative process, ATCO was found to have sole-sourced a contract at above-market rates. The AUC completed a separate process to determine penalties for ATCO Electric.