On April 4, 2017 the AUC approved the AESO 2017 Tariff in Decision 22093-D02-2017.
To view more of this post, please
On April 4, 2017 the AUC approved the AESO 2017 Tariff in Decision 22093-D02-2017.
To view more of this post, please
On December 16, 2016, the AUC released Decision 20414-D01-2016 the second generation of Performance Based Regulation (2018-2022).
To view more of this post, please
On December 2, 2016, the AUC approved an interim tariff for 2017 after concluding that the current hearing would not be completed in time for the AESO requested deadline of December 28, 2016.
To view more of this post, please
On September 6th, the Market Surveillance Administrator released two “Retail Market Reports” titled Assessment of Inter-jurisdictional Retail Rate Comparisons and Trends in Regulated Retail Electricity and Natural Gas Bills.
To view more of this post, please
In a recent R&V Decision*, the AUC directed Canadian Utilities Limited (CUL) to produce documents related to the successful bid for the Fort McMurray West 500kV Transmission Line project.
To view more of this post, please
On January 13, 2016 ATCO Electric (AE) responded to a fourth round of IRs in their 2016-2017 General Tariff Application proceeding. And on January 20, 2016 interveners submitted a third round of evidence, with IRs and intervener responses to IRs following on February 1st and 11th respectively.
To view more of this post, please
On January 18, 2016 the Alberta Utilities Commission released decision (20456-D01-2016), denying an application from the Alberta Utilities to review and vary the 2013-2015 Generic Cost of Capital Decision.
To view more of this post, please
In September of 2015, the AESO submitted an application to the AUC for approval of their 2013 and 2014 deferral account reconciliation.
To view more of this post, please
Both AltaLink and ATCO Electric (AE) are in the midst of 2015-2016/17 tariff application proceedings. Having filed their initial applications towards the end of 2014, both utilities have recently submitted updates to their tariff applications. The proposed revisions are largely in response to changing economic conditions in Alberta.
To view more of this post, please
As part of the ATCO Electric 2015-2017 GTA proceeding, the Alberta Utilities Commission ordered Canadian Utilities Limited (CUL), the corporate parent of ATCO Electric to turn over any documents related to their subsidiary’s (Alberta Powerline Limited Partnership) successful bid for the Fort McMurray West 500kV Transmission Line project.